TIME RECORDED AND TRANSCRIBED NOTES FOR RODGER C. WHITE
FOR: RONAN/MOSELEY/TITAS GAS T&D CO. LTD. - BRAMAPUTRA BASIN T&D PROJECT
HOURS WORKED (NOT INCLUDING BRAKES)
|
D# |
DW |
DATE |
HRS -¼ HR |
COMMENTS |
|
1 |
F |
6/18/93 |
10.00 |
CHECK OUT COMPONENTS AND ARRANGE
TRIP. |
|
|
|
|
|
|
|
2 |
S |
6/19/93 |
14.00 |
MEET JH IN STA BARBARA. THEN TO RONAN
TO PACK MATERIALS |
|
|
|
|
|
|
|
3 |
S |
20 |
10.00 |
LAX - SF / SF TO TOKYO |
|
|
M |
21 |
|
TOKYO - BANKOCK |
|
|
|
|
|
|
|
4 |
T |
22 |
10.00 |
BANGKOK-DHAKA - MEET AT TWX-TOUR
TITAS - C/O MATERIAL IN STORAGE - THE PACKING CRATE IS PARTIALLY OPEN AT THE
BOTTOM AND THE PROTECTIVE PLASTIC IS TORN TO ABOUT 2.5 OR 3FT. I AM INFORMED THAT THE PANEL MUST BE
CARRIED TO THE 7TH FLOOR - 8 FLIGHTS OF STAIRS, NARROW, DOWN A HALL AND INTO A SMALL ROOM. NEITHER TWX NOR TITAS GAS POSSES THE
RESOURCES TO TRANSPORT THE PANEL IN ONE PIECE. PLAN DISASSEMBLY STRATEGY AND PREPARE DIRECTIONS. |
|
|
|
|
|
|
|
5 |
W |
23 |
10.00 |
UNPACK, DISASSEMBLE, MOVE,
RE-ASSEMBLE AND INSTALL ALARM PANEL
AT TITAS OFFICE (SEE PICS) THE
CABINET RECEIVED SEVERAL SCRATCHES IN THE MOVE. DISPLAY, RACKS, AND MODULES
ALL APPEARED OK AFTER THE MOVE.
POWER SUPPLY NOT OPERATING.
POWER TO PANEL NOT WIRED - IE. NO LINE FROM PS TO PANEL. COMPUTER 110-220 SWITCHABLE. MONITOR 110 ONLY. NEED TWO BAYONET TYPE PLUG CONVERTERS AND
A 110-220 CONVERTER. CHECKED POWER
SUPPLY ON PORTABLE. NEEDS 110. |
|
|
|
|
|
|
|
6 |
T |
24 |
8.00 |
ARRANGE FOR EQUIPMENT - 220-110
CONVERTER, EXTENSION CORD, MULTI PLUG, MEET WITH SHAHIN ISLAM AND TWX
TECHNICIANS, ASKED FOR SIGNAL LIST - DIDN'T KNOW WHAT I MEANT. NO KEYBOARD FOR THE COMPUTER NOR ANY SPARE
PARTS, NO CABLE TO CONNECT COMPUTER TO MTU. |
|
|
|
|
|
|
|
7 |
F |
25 |
8.00 |
LOCATED TWX VARIABLE PS 15V/20AMP -
TRIED TO LOCATE SIGNAL LIST FROM CUSTOMER TO BEGIN LABELING THE ALARMS AND
PROCESS SIGNALS, SEARCHED FOR MISSING COMPONENTS FROM FEBRUARY SHIPMENT. (SEE NOTES FOR SEPT. 18) |
|
|
|
|
|
|
|
8 |
S |
26 |
10.00 |
BEGAN TESTING MTU/RTU'S PREPARATORY
TO MOVING RTU'S TO REMOTE LOCATIONS - RECEIVED SIGNAL LIST FROM TWX PROVIDED
TO THEM BY THE CUSTOMER. IT APPEARS
THAT THE CUSTOMER MAY HAVE 12 PROCESS SIGNALS, WE ONLY PROVIDED FOR 6. NO ONE AVAILABLE TO VERIFY OR
CLARIFY. TRIED AGAIN TO SEARCH FOR
MISSING SIGNAL LIST. TWX INSISTS THAT
NONE WAS RECEIVED. TWX ALSO INSISTS THAT NO SPARES, NO CABINET KEYS, NOR
OTHER MATERIALS WERE RECEIVED. |
|
|
|
|
|
|
|
9 |
S |
27 |
8:00 |
DC-DC CONVERTER AT TITAS OFFICE IS
12-24VDC, SUPPLY IS 24 VDC. CANNOT TEST PANEL. CONTINUED TESTING RTU'S USING
15V VARIABLE SUPPLY. |
|
|
|
|
|
|
|
10 |
M |
28 |
12:00 |
VISITED SHERPUR AT INSISTENCE OF
SHAHINUL ISLAM. DAMAGE REPORTED TO TELEMETRY
CABINET AND PANEL. LEFT TWX OFFICE
FOR SHERPUR AT 10:00 AM - 4.5 HR DRIVE.
SWINGING MODULE RACK HAD BECOME UNHINGED DURING SHIPMENT OVER ROUGH
ROADS. IT HAD BOUNCED AROUND ABRADING
THE EXTRUDED ALUMINUM TRIM AND COVER PLATES, BENDING THE SCREWS AND TEARING
THE WIRES ON THE BACK OF THE ALARM PANELS.
THE RETAINING BRACKET WAS CRACKED, THE TOP BRACKET WAS LOOSE, AND THE
SIDE BRAISES IN THE CABINET WERE BENT.
THE CABINET WAS SCRATCHED. TWO
OF THE LOGIC |
|
10 |
M |
28 |
12:00 |
RELAYS WERE DESTROYED AND THE ELCO
CONNECTORS FROM THE ALARM MODULES TO THE ALARM WERE BENT AND THE CASE OF ONE
WAS CRACKED. SEVERAL SCREWS WERE
MISSING FROM THE TERMINAL BLOCKS. |
|
|
|
|
|
1. REMOUNTED SWING RACK. |
|
|
|
|
|
2. REPAIRED, REBUILT ELCO CONNECTORS, STRAIGHTENED |
|
|
|
|
|
KEEPER SCREWS AND STRAIN RELIEF.
ALL POINTS |
|
|
|
|
|
EXHIBITED CONTINUITY ON DIGITAL MULTI METER (DMM). |
|
|
|
|
|
3. STRIPPED, TWISTED, WIRE NUTTED AND TAPED THE |
|
|
|
|
|
SEVERED WIRES. CONFIRMED
CONTINUITY WITH DMM. |
|
|
|
|
|
4. USED BLANK PANEL SCREWS TO REMOUNT LOOSE |
|
|
|
|
|
TELEMETRY RACK. |
|
|
|
|
|
5. USED EXTRA TERMINAL BLOCK (TB) SCREWS TO LAND |
|
|
|
|
|
SEVERED WIRES. |
|
|
|
|
|
THE TELEMETRY CABINET SITS BY A
WINDOW, NO SHADE. THE METAL TOWARD THE WINDOW WAS QUITE WARM TO THE
TOUCH. THERE IS ANOTHER WINDOW ON THE
OPPOSITE WALL - ABOUT 6' AWAY. WITH
THE WINDOWS OPEN THE CABINET IS ESSENTIALLY OUTSIDE. THE SAME IS TRUE OF THE TERMINATING
CABINET FOR THE METERING EQUIPMENT. |
|
|
|
|
|
THERE WAS NO ELECTRIC POWER AT THE
SITE AND NO GENERATOR - ALSO NO RUNNING WATER, THE GUARDS WERE COOKING WITH
WOOD ON THE FLOOR AND SLEEPING ON THE DESKS AND ON WOODEN PLATFORMS WITH THIN
PADS. GOATS AND CATTLE WERE GRAZING IN THE PIPE FIELD. THERE WERE NO SANITARY FACILITIES. |
|
|
|
|
|
|
|
11 |
T |
6/29/03 |
6:00 |
INVENTORIED EQUIPMENT ON HAND - (SEE
LIST) MISSING EXTRA LAMPS, SPARE ALARM MODULES, FILTERS, FLASHERS, AND LOGIC
UNITS FOR REMOTE SITES. TWX CLAIMS
NEVER RECEIVED. |
|
|
|
|
|
|
|
12 |
W |
6/30/03 |
11:00 |
TITAS - STILL NO CONNECTION FROM SYSTEM POWER SUPPLY SO SET UP TEMPORARY POWER
SUPPLY USING 15VDC VARIABLE SUPPLY FROM TWX AND TESTED PANEL LIGHTS BY
SHORTING EACH LAMP TO COMMON.
MYMENSINGH #7 BURNED OUT. REPLACED WITH LAMP FROM THE "KEY"
ARRAY. TEMPORARY SUPPLY NOT SUFFICIENT TO LIGHT ALL LAMPS AT ONE TIME NOR TO
OPERATE FLASHERS WHEN ALL LIT. IT APPEARS THAT ONE OR MORE FLASHERS WILL NOT
WORK IN THE "MASTER" POSITION. EACH ALARM FLASHED AND WENT STEADY @
ACKNOWLEDGE INDIVIDUALLY. |
|
|
|
|
|
|
|
13 |
T |
7/01/03 |
9:00 |
TEST RTU'S AND MTU'S. ONLY TWO WORKED OF THE 6 TESTED. ALL HAD WORKED AT THE FACTORY IN FEBRUARY.
NOR THE SPARES I HAD CARRIED, ALL
WORKED. PROBLEM WITH RAI? TYPE FAX TO
RONAN RE: LIGHT PANEL AND TO WKD RE RAI. (TITAS CLOSED - SOME SORT OF
RELIGIOUS HOLIDAY- LONG WEEKEND) |
|
|
|
|
|
|
|
14 |
F |
7/02/03 |
4:00 |
TWX OFFICE CLOSED (HOLIDAY, SABATH)
WORK ON CFG CHANGES. NO RESPONSE TO
FAXs. TAKE PM OFF - GO TO ZOO. |
|
|
|
|
|
|
|
15 |
S |
7/03/03 |
9:50 |
TEST MTU AND RTUs AT TITAS. 4 RTUs OK, PROBLEM W/ SPARE MTU. SEND 2ND FAX TO WKD RE RAI. PROBLEM WITH CD IN NEW MODEM UNITS. |
|
16 |
S |
7/04/03 |
10:00 |
TWX OFFICE - NO REPLY TO FAXs TITAS- TRACED CIRCUIT ON RAI --- DIAGRAM ON TOP
OF RELAY WAS MIRROR IMAGE OF PINOUTS.
FIXED WITH CUT AND PATCH. PUT EACH CENTRAL RTU IN PANEL (2,3, &
4) 1 AT A TIME. ALL WORKED. REPAIRES
TO OTHER RTUs. |
|
|
|
|
|
|
|
17 |
M |
7/05/03 |
12:00 |
TWX
OFFICE - NO REPLY TO FAXs. MEETING WITH JAMAL HAMDANI @ TITAS OFFICE
- TEST AND REPAIR RTU'S 3 AND 4. THEY WERE NOT CONNECTED TO THE MTU AT ALL.
FIXED THROUGH RAI. |
|
|
|
|
|
MTU RX AND TX
REVERSED TO RAI. CORRECTED. |
|
|
|
|
|
REMOVED
EXTRANIOUS WIRES FROM T4 AND T5 ON RTU CHASSIS 1,2, AND 3. |
|
|
|
|
|
ALL ORIGINAL
MODEM BOARDS WORKING FINE. REVISED
BOARDS RESPOND TO MTU, MTU HEARS BUT DOES NOT UNDERSTAND IF MORE THAN ONE IN
RACK. IF REVISED BOARD IN RACK WITH
ORIGINAL, MTU HEARS BOTH BUT ONLY UNDERSTANDS THE NEW BOARD. |
|
|
|
|
|
WHEN RAI
PRESENT, MTU SDI BLINKS IN CONJUNCTION WITH SDO. THIS DOES NOT APPEAR TO AFFECT OPERATION. SPARE MTU, SPARE RTU, AND ORIGINAL RTU
NEED TO BE REPAIRED. |
|
|
|
|
|
CHASSIS
NOTES: SCREWS ON RTU CHASSIS 2 AND 3
ARE CORRODED. SCREWS ON THE ALARM
CHASSIS AND RTU CHASSIS 1 ARE BRIGHT AND SHINEY. THE CRATE WAS OPEN AND THE
PLASTIC COVER TORN TO ABOUT THE SAME HEIGHT. |
|
|
|
|
|
|
|
18 |
T |
07/06/93 |
10.25 |
TITAS OFFICE - CONTINUTE RTU TEST AND
REPAIR. CHECK OUT POWER SUPPLY. CAN IT BE CONVERTED TO 24-24. NO! |
|
|
|
|
|
POWER SUPPLY NEEDED BY TWX. NO POWER AT TITAS. RETURN TO TWX AND TYPE REVISIONS TO
OPERATORS MANUAL SPECIFIC TO TITAS SYSTEM. |
|
|
|
|
|
|
|
19 |
W |
07/07/93 |
10.50 |
TWX OFFICE - CONTINUE OPERATORS
MANUAL - TRAIN M. NASIMNUL HOQ TO OPERATE SYSTEM AND EDIT CFG FILES - ENTER
NAMES OF SIGNALS PROVIDED BY TITAS. |
|
|
|
|
|
|
|
20 |
T |
07/08/93 |
10.50 |
TWX OFFICE - CONTINUE OPERATORS
MANUAL - CONTINUE NASIM'S TRAINING. (FINISHED, REREAD AND REVIEW.) |
|
|
|
|
|
|
|
21 |
F |
07/09/93 |
3.00 |
TWX TOOK 24-24 DC-DC CONVERTER FROM
BHALUKA FOR THE TITAS CENTRAL. TITAS
OFFICE CLOSED - COULD NOT INSTALL
P.S. |
|
|
|
|
|
REREAD MANUAL, REVISE |
|
|
|
|
|
|
|
22 |
S |
07/10/93 |
11.50 |
TWX HAS
INSTALLED WIRING FROM RADIO TO PANEL AND
RAN 24 VDC POWER TO PANEL SOME TIME IN LAST WEEK. I INSTALLED 24-24 CONVERTER FROM
BHALUKA. DISCONNECTED OUTPUT. TESTED. 24 VDC IN, 23.7 OUT. RECONNECTED OUTPUT, TESTED PANEL LIGHTS -
OK. |
|
|
|
|
|
DRIVE TO BHALUKA
TO REPALCE 24-24 VDC CONVERTER WITH THE 12-14 VDC CONVERTER FROM
CENTRAL. OUTPUT FROM POWER SUPPLY TO
TELEMETRY CABINET NOT YET CHANGED TO 12 VDC |
|
|
|
|
|
RETURNED TO
TWX OFFICE. CONFERED WITH SHAHADAD HOSSAIN RE. SWITCHING TELEMETRY POWER
SUPPLY AT BHALUKA TO 12 VDC. |
|
|
|
|
|
|
|
23 |
S |
11 |
11.50 |
BHALUKA
- MAI IN J2, MOVE TO J3, INSTALL RTU AND AST.
POWER CABLE STILL CONNECTED TO 24VDC, NOT LANDED IN TELEMETRY PANEL. UNPLUGGED
ALL MODULES UNTIL POWER CORRECTLY INSTALLED.
SUN SHINES IN WINDOW BY PANEL MAKING IT VERY HOT. NO AIR CONDITIONER. INSECTS FILLING CABINET, SPIDER WEBS A
PROBLEM. NEED SHADE IN WINDOW,
EXTERMINATOR, AIR SO THAT WINDOW CAN BE KEPT CLOSED. |
|
|
|
|
|
TRISHAL
- MOVE MAI FROM J2 TO J3, INSTALL RTU AND AST. 12VDC FROM POWER SUPPLY TO TELEMETRY
NOT CONNECTED AT POWER SUPPLY NOR
LANDED ON TELEMETRY. NO 120 SERVICE.
PROBLEM WITH WINDOW BY CABINET SAME AS BHALUKA. |
|
|
|
|
|
MYMENSINGH
- VERIFIED 24 VDC SUPPLY, 24-24 VDC
CONVERTER. JUMPERED FROM SUPPLY CABLE
TO CONVERTER. INSTALL RTU AND AST, MOVED RAI TO J3. CHANNELS 2, 3, AND 4
OVERRANGED ON MAI. |
|
|
|
|
|
TEST ON RONAN
PANEL LIT ALL LIGHTS. GETTING
DARK. TWX INSITED ON RETURNING TO
DHAKA. |
|
|
|
|
|
REMOVED POWER
JUMPER. TWX TO LAND POWER
PERMINANTLY. |
|
|
|
|
|
PROBLEM WITH
WINDOW SAME AS AT TRISHAL AND BHALUKA. |
|
|
|
|
|
24 M 12
11.25 TITAS OFFICE TO PICK UP
RTU AND AST FOR ASHUGONJ RAIN HAD
LEAKED IN AROUND AIR CONDITIONER - .25" FLOWING UNDER PANEL. 220-110 CONVERTER SURGING? ALSO NEED
220-110 CONVERTER TO OPERATE MONITOR AT TITAS CENTRAL. |
|
|
|
|
|
TWX OFFICE
FOR MEETING |
|
|
|
|
|
ASHUGONJ - VERIFY 24 VDC POWER - OK |
|
|
|
|
|
VERIFY RONAN
PANEL ALARMS, OK |
|
|
|
|
|
RTU - SCANNER
COMMUNICATION APPEARS OK |
|
|
|
|
|
AST CH 1-4
OVER RANGE WHEN MAI PRESENT. |
|
|
|
|
|
( GUARD
SLEEPING ON DESK IN TELEMETRY ROOM, RAIN COMMING IN WINDOW BY PANEL, WASH
LINE STRUNG BETWEEN TELEMETRY AND METER PANEL WITH WASH DRYING. ) |
|
|
|
|
|
|
|
24 |
M |
11 |
11.25 |
TITAS OFFICE TO PICK UP RTU AND AST FOR ASHUGONJ.
RAIN HAD LEAKED IN AROUND AIR CONDITIONER - 1/4" FLOWING UNDER
PANEL. 220-110 CONVERTER
SURGING? ALSO NEED 220-110 CONVERTER
TO OPERATE MONITOR. BACK TO TWX
OFFICE FOR MEETING |
|
|
|
|
|
ASHUGONJ - VERIFY 24 VDC POWER - OK.
VERIFY RONAN PANEL ALARMS, OK
RTU - SCANNER COMMUNICATION APPEARS OK. AST CH 1-4 OVER RANGE WHEN MAI PRESENT. |
|
|
|
|
|
( GUARD SLEEPING ON DESK IN TELEMETRY
ROOM, RAIN COMMING IN WINDOW BY PANEL, WASH LINE STRUNG BETWEEN TELEMETRY AND METER PANEL WITH WASH
DRYING. ) |
|
|
|
|
|
|
|
25 |
T |
13 |
12.00 |
TITAS OFFICE - BILL ROBERTS, FROM RADIO COMPANY,
CLAIMED READY TO TEST RADIO LINK.
NO PROVISION FOR LINKING RADIO TO MTU. RADIO NOT WORKING ANYWAY.
DRIVER HAD LEFT, CALLED TWX FOR PU TO CHECK OUT STORAGE FOR
SPARES. TRANSPORT DID NOT ARRIVE FOR
SOME TIME - 1.5 HOURS. NO ONE WITH
KEY FOR STORAGE SO WENT IN SEARCH OF KEYBOARD. |
|
|
|
|
|
PROCURED KEYBOARD FOR MATRIX
COMPUTER. |
|
|
|
|
|
|
|
25 |
T |
13 |
|
(NOTE: SPENT A TOTAL OF 2 HOURS
WAITING FOR TRANSPORT FROM TWX. THIS
HAS BEEN AN ONGOING PROBLEM. THEY ARE
SCHEDULED TO ARRIVE AT 8:00 OR 8:30.
THEY SHOW ANY TIME BETWEEN 7:30 AND 10:00. THIS MORNING IT WAS ABOUT 9:30. I'M GETTING TICKED.
THEY DON'T CALL THEY JUST SHOW UP AND EXPECT ME TO BE WAITING. IF THEY ARE LATE, I GO TO WORK IN MY ROOM
AND DO WHAT I CAN UNTIL THEY ARRIVE.
MY BLOOD PRESSURE IS VERY HIGH AND I AM VERY IRRITATED. REQUESTS TO TWX ARE IGNORED. DEMANDS RECEIVE A POLITE HEARING BUT
NOTHING CHANGES. NO ONE AT TWX
UNDERSTANDS HOW THE SYSTEM WORKS NOR ARE THEY PARTICULARLY INTERESTED IN
FINDING OUT - WITH THE EXCEPTION OF NASIM.) |
|
|
|
|
|
(VERY ILL, PROBLEM WITH TEMPER
CONTROL.) |
|
|
|
|
|
|
|
26 |
W |
14 |
11.25 |
TITAS GAS - TESTED MODULES WHILE WAITING FOR RADIO RADIO NOT OPERATIONAL FOR TELEMETRY. ACTUALLY, THE WHOLE
RADIO SYSTEM WAS DOWN DUE TO A FAILURE AT ONE OF THE MICROWAVE SITES. |
|
|
|
|
|
TWX OFFICE - WORKED ON HOST COMPUTER
- IT WOULD NOT BOOT UNDER CONCURRENT
DOS. CHEAP KEYBOARD. WOULDN'T
WORK WITH KEYBOARD FROM TWX COMPUTER EITHER. |
|
|
|
|
|
NOTE: WAS TO BE PICKED UP AT
8:30. TWX ARRIVED AT 10:20.
WENT TO TWX OFFICE WHERE DISCUSSIONS ABOUT GAS FOR CAR AND OTHER FALDERAL TOOK 30 MINUTES. WAS
UNABLE TO START WORK UNTIL ALMOST NOON. I'M PISSED! |
|
|
|
|
|
|
|
27 |
T |
15 |
11.00 |
TITAS GAS - PROBLEM IN ANN PANEL. TRACED
TO SHORT IN CIRCUIT FROM TEST SWITCH.
REMOVED TEST SWITCH. TESTED ALARM MODULES INDIVIDUALLY. ALL WORKED AND FLASER WORKED. NEED NEW SWITCH. |
|
|
|
|
|
NO POWER OUTLET FOR PANEL. ONLY OUTLET AVAILABE TAKEN BY RADIO
CHARGER. |
|
|
|
|
|
PURCHASED OUTLET ADAPTER AT STADIUM
ELECTRONICS MART SO THAT TWO COMPUTERS COULD BE USED AT GUEST HOUSE. |
|
|
|
|
|
WENT TO STORAGE CONTAINER AT VENTURA
AUTO REPAIR TO SEARCH FOR MISSING SPARE PARTS. COULD NOT LOCATE ANY PARTS FOR THIS JOB EXCEPT COMPUTER FOR
RADIO SCADA. |
|
|
|
|
|
TESTED REMAINING RTUs, MTUs AND
ASTs. 6 RTUs, 2 MTUs, NOT FUNCTIONAL. |
|
|
|
|
|
MEETING AT TWX WITH BAHADUR AND ISLAM
RE MAINTINANCE. RADIOS STILL NOT
OPERATIONAL. |
|
|
|
|
|
|
|
28 |
F |
16 |
----- |
ALL CLOSED ON FRIDAY - ILL, FEVER AND
COLD. DAY IN BED RECOUPERATING. |
|
|
|
|
|
|
|
29 |
S |
17 |
8.00 |
APPOINTMENT TO BE PICKED UP AT
8:00. CAR ARRIVED AT 9:00 A.M. WAITED 1.5 HOURS AT TWX OFFICE TO GO TO
TITAS. ARRIVED AT TITAS AT 10:40.
TITAS ENGINEER - ANAMESH CHAKMA - WANTED DEMO. |
|
|
|
|
|
RADIO STILL NOT FUNCTIONING AND NO
CABLE FROM RADIO TO TELEMETRY PANEL - STILL!
RADIO TECH HAD NO IDEA HOW TO CONNECT RADIO TO TELEMETRY. |
|
|
|
|
|
|
|
30 |
S |
18 |
8.00 |
WORK AT GUEST HOUSE - TRAIN NASIM -
OPERATION, TROUBLE SHOOT, CONFIGURATION. |
|
|
|
|
|
|
|
31 |
M |
19 |
11.00 |
BHALUKA - SHAHINUL SWITCHED POWER FROM 24 TO 12VDC SUPPLY. VERIFIED 12 VDC AT
TELEMETRY CABINET. LANDED POWER. OK. |
|
|
|
|
|
TRISHAL - SHAHINUL VERIFIED 12 VDC WIRED CORRECTLY AT PS. VERIFIED THAT CORRECT CABLE IN TELEMETRY
CABINET. LANDED POWER CABLE. - BUT - NO AC SO COULD NOT CHECK IT OUT. |
|
|
|
|
|
MYMENSINGH - SHAHINUL VERIFIED 24 VDC AT SUPPLY. VERIFIED 24 VDC AT TELEMETRY
CABINET. LANDED POWER. OK. |
|
|
|
|
|
|
|
32 |
T |
20 |
11.00 |
VISITED MYMENSINGH, TRISHAL,
AND BHALUKA WITH TITAS ENGINEERS - ANAMESH CHAKMA, MR. MAMUD - AND
SHAHIN ISLAM. DISCUSSED WHICH SIGNALS WERE TO BE LANDED AND WHERE. WHETHER NO OR NC. TITAS WAS NOT SURE WHICH WERE NO OR
NC. NOT AWARE WHERE SIGNALS CAME IN.
WOULD GET BACK TO SHAHIN. |
|
|
|
|
|
TITAS ENGINEERS REQUESTED THAT MODULE
LABLES BE WRITTEN ON EACH MODULE. COMPLIED. AGREED TO DO THE SAME AT ALL
SIGHTS. |
|
|
|
|
|
ALARM AST'S OVER-RANGING. TRIED 269 OHM RESISTORS FROM AST T6, T7, T8,
T9 TO COMMON. OVER RANGE DISAPPEARED (CONVERTED 4-20mA TO 1-5 VDC.) |
|
|
|
|
|
REMOVED MAI FOR MODIFICATION. |
|
|
|
|
|
|
|
33 |
W |
21 |
10.00 |
TITAS OFFICE - TWX RAN CABLE TO RADIO. LAND
CABLE. 3 WIRE CONNCETION. NOT
COMMUNICATING ON RADIO. WILL NOT TALK TO REMOTE SITES. TALKS JUST FINE TO LOCAL RTUs. SDI BLINKS WITH SDO. DOES NOT WHEN |
|
|
|
|
|
RADIO LEADS TO TB3,2 LIFTED. RADIO TECHNITION STILL CANNOT TELL ME HOW
TO INTERFACE WITH RADIO. HE SAIS
SOMETHING ABOUT NEEDING 4 WIRE CONNECTION.
THAT WAS NOT IN SPECS. CHANGE
ORDER TO PROVIED 4 WIRE. WILL REQUIRE
REWIRE ON RONAN PANEL. |
|
|
|
|
|
RETURNED TO TWX OFFICE - WENT TO
STADIUM ELECTRONICS MARKET - PURCHASED 180 OHM AND 69 OHM RESISTORS TO
PRODUCE 249 OHMS - ALSO SOME IN4148 DIODES. |
|
|
|
|
|
MODIFIED SPARE MAIs WITH RESISTORS -
289 OHMS BETWEEN TERMINALS 6, 7, 8, AND 9 TO TERMINAL 1, COMMON TO CONVERT
4-20mA TO 1-5VDC. |
|
|
|
|
|
|
|
34 |
T |
22 |
10.50 |
TITAS OFFICE IN AM - RADIO TECHS
STILL DO NOT HAVE THE SCADA RADIO OPERATIONAL NOR CAN THEY GIVE ME AN ANSWER
RE THE NECESSITY TO CONVERT TO 4 WIRE FROM THE 3 WIRE PROVIDED. |
|
|
|
|
|
RETURN TO TWX OFFICE / MODIFY MORE
MAIs. TWX WILL BRING IN REST. |
|
|
|
|
|
|
|
35 |
F |
23 |
8.00 |
TWX - REPRINT OPERATORS MANUAL. WORK ON FIELD. OPERATORS MANUAL. MASTER WAS DELIVERED TO TWX ON THE
15TH. THEY CANNOT FIND IT. SO
REPRINTED. |
|
|
|
|
|
NOTE: HEART ATTACK AT 7:00 PM. HOSPITAL AT 9:30. |
|
|
|
|
|
|
|
36 |
S |
24 |
----- |
HOSPITAL ICU |
|
|
|
|
|
|
|
37 |
S |
25 |
----- |
HOSPITAL ICU |
|
|
|
|
|
|
|
38 |
S |
26 |
----- |
HOSPITAL MONITOR |
|
39 |
T |
27 |
4.00 |
RETURN TO GUEST HOUSE FROM HOSPITAL
AT 3:00 P.M. TYPE REPORTS AND WORK ON FIELD MANUAL. |
|
|
|
|
|
|
|
40 |
W |
28 |
8.00 |
CONTINUE WORK ON FIELD MANUAL. MEET WITH SHAHINUL ISLAM RE RADIO HOOKUP
AND COMPUTER INTERFACE. |
|
|
|
|
|
|
|
41 |
T |
29 |
8.00 |
CONTINUE WORK ON FIELD MANUAL. MEET WITH ROBERTS RE RADIO AND HOW TO INTERFACE WITH IT. FINISHED
FIELD MANUAL. |
|
|
|
|
|
|
|
42 |
F |
30 |
9.00 |
MEET @ TWX - BEGIN
CONFIGURATION MANUAL FOR TWX |
|
|
|
|
|
|
|
43 |
S |
31 |
11.50 |
MEET @ TWX - TRY MATRIX
COMPUTER 1 MORE TIME - WILL NOT
BOOT. CONTINUED WORK ON CONFIGURATION
MANUAL AT OFFICE AND AT GUEST HOUSE. |
|
|
|
|
|
|
|
44 |
S |
8/01/93 |
9.00 |
TWX OFFICE - BOOT MATRIX UNDER DOS 5.9 - OK WITH
DISKETTE. INSTALLED DOS 5.0 ON HARD DISK. NO GO. REFORMATED MATRIX
HARD DISK AND REINSTALLED 5.0. STILL NO GO.
CONCLUDED MATRIX DEAD FOR ONE REASON OR ANOTHER. CONTINUED WORKING ON CONFIGURATION MANUALS.
|
|
|
|
|
|
|
|
45 |
M |
02 |
9.00 |
MEET AT TWX - TYPE REPORTS FOR
TP AND RONAN - CONTINUE WORK ON CONFIGURATION MANUAL |
|
|
|
|
|
|
|
46 |
T |
03 |
10.00 |
PRINT CONFIGURATION MANUAL, CONTINUE
WITH MAI MODS |
|
|
|
|
|
|
|
47 |
W |
04 |
11.00 |
PROGRAM EEPROM TO TALK ONLY TO
BHALUKA. |
|
|
|
|
|
BHALUKA - RADIO LINK DOES NOT WORK.
NO COMMUNICATION ON SCADA CHANNEL.
TWX TRIED BUT CANNOT COMMUNICATE WITH OTHER SITES EITHER. RADIO OUT OF SERVICE. |
|
|
|
|
|
RETURN TO DHAKA, MODIFY MORE MAIs. |
|
|
|
|
|
|
|
48 |
T |
05 |
9.50 |
NO RADIO SCADA LINK. TWX AND ROBERTS
WORKING ON PROBLEM. SEEMS TO BE IN
MONOHORDI OR DEMERA. |
|
|
|
|
|
RADIO KEY ALWAYS LOW. LIFTED LEAD TO RADIO AND PROBLEM
DISAPPEARED. RADIO PERMINANTLY KEYED.
TWX AND ROBERTS NOT SURE WHY. |
|
|
|
|
|
MODIFY MORE MAIs. |
|
|
|
|
|
|
|
49 |
F |
06 |
6.00 |
TWX REPORTS RADIO NOT WORKING. NO USE GOING TO TITAS. FINISH MAI MODs. WORK ON BAD UNITS. MAKE MODIFICATIONS TO FIELD MANUAL. |
|
|
|
|
|
|
|
50 |
S |
07 |
10.00 |
APPOINTMENT TO BE PICKED UP AT 7:30
A.M. TO GO TO TITAS AND BHALUKA TO WORK ON GETTING SIGNAL THROUGH RADIO THAT
TWX REPORTED NOW HAD A SCADA CHANNEL. |
|
|
|
|
|
CAR ARRIVED AT 10:30, NO CALL. WORKED ON FIELD MANUAL WHILE WAITING FOR
CAR. BLOOD PRESSURE HIGH AND ANGER
INCREASING. |
|
|
|
|
|
PROGRAMMED EEPROM TO HIT EACH DSR
POINT IN TURN AND LIGHT EACH LIGHT.
ALL WORKED OK. |
|
|
|
|
|
RADIO LINK - |
|
|
|
|
|
PROGRAMMED EEPROM TO TALK TO
CO-LOCATED RTUs AND BHALUKA. MTU
TALKED TO CO-LOCATED RTUs BUT RECEIVED NO RESPONSE FROM BHALUKA. DROVE TO
BHALUKA. |
|
|
|
|
|
BHALUKA - NO SDI ON RTU. LIFTED THE
RADIO KEY LINE. STILL NO SDI. RETURN TO TITAS CENTRAL. |
|
|
|
|
|
TITAS CENTRAL - MTU SDI FLASHES WHEN SDO
FLASHES. REMOVE RAI. SDI DOES NOT
FLASH. |
|
|
|
|
|
TIED RADIO XMIT LEAD FROM MTU TO
CO-LOCATED RTU. WORKED. XMIT IS GOING OUT. NEED A SCOPE. TWX SCOPE STILL NOT WORKING. |
|
|
|
|
|
RECONNECT TO RADIO, REINSTALL
RAI. RTUs WHICH HAD BEEN WORKING
QUIT. RTU'S ARE APPARENTLY HEARING
THE MTU BUT NOT RESPONDING. LEVEL
PROBLEM. SYMPTOMS NOT OBSERVED
EARLIER. |
|
|
|
|
|
WHEN LIFT RADIO KEY LEAD TO RADIO,
MTU HEARS RTUs. REATTACHED KEY LEAD.
SOMETHING ON RADIO SIDE HOLDING THE KEY HIGH, THEN LETTING IT
"FADE" BUT IT NEVER GETS TO 0. LOWERED GAIN IN RAI. MTU UNDERSTANDS RTU RESPONSES. |
|
|
|
|
|
|
|
51 |
S |
08 |
10.00 |
TITAS CENTRAL - VERIFIED TX AND RX FROM RAI. TESTED REMAINING RTUs IN TEST RACK. ALL
OK. |
|
|
|
|
|
REVERIFIED TX AND RX THROUGH RAI T13
AND T14. FIX RTU DESIGNATION MIXUP BETWEEN MYMENSINGH AND TARAKANDI. TARAKANDI-17, MYMENSINGH-15. |
|
|
|
|
|
MAKE A BOOTABLE SCADA DISKETTE TO
TEST REPLACEMENT COMPUTER. |
|
|
|
|
|
CONFER WITH ROBERTS RE RADIO AND
RADIO CONNECTIONS TO THE COMPUTER.
ROBERTS BELIEVES THAT 4 WIRE MODS ARE NECESSARY. DOESN'T THINK KEY AT CENTRAL NEEDED.
APPARENTLY NOT. |
|
|
|
|
|
RESPOND TO FAX INQUIRY. |
|
|
|
|
|
|
|
52 |
M |
09 |
12.00 |
TITAS OFFICE - SDI STILL BLINKS WHEN SDO BLINKS IF RADIO ATTACHED. |
|
|
|
|
|
SDO DOES NOT BLINK WHEN CO-LOCATED
RTU RESPONDS. |
|
|
|
|
|
SDO BLINKS WITH SDI WHEN REMOTE RTU
RESPONDS. |
|
|
|
|
|
LISTEN TO TX AND RX, CAN HEAR TX ON
RX LINE AND RX ON TX LINE. |
|
|
|
|
|
LIFTED RADIO LEADS. CANNOT HEAR TX ON RX NOR RX ON TX. |
|
|
|
|
|
CONFER WITH ROBERTS AND SHAHADAD
HOSSAIN RE SOLUTIONS LIFT RADIO KEY LEAD TO RADIO. TB3,1 W/B(TX) TB3,2 B/W (RX)
TB3,3 NC(RKEY) TB3,4 G/W
(COMMON) |
|
|
|
|
|
PROGRAM EEPROM TO TALK TO BHALUKA,
TRISHAL, AND MYMENSINGH. |
|
|
|
|
|
BHALUKA - CHECK OUT INDIVIDUAL ALARMS BY GROUNDING EACH INPUT. ALL OK. |
|
|
|
|
|
INSTALL MODIFIED MAI. |
|
|
|
|
|
SWAP J1 T4 AND T6 - RX AND TX. |
|
|
|
|
|
RTU HEARING MTU BUT NOT
UNDERSTANDING. |
|
|
|
|
|
DOESN'T UNDERSTAND MESSAGE. |
|
|
|
|
|
TRISHAL - WIRE MODS, RTU NOT HEARING
MTU. CHECK OUT ALARM PANEL. SEE CHECKOUT SHEET. |
|
|
|
|
|
INSTALL MODIFIED MAI. |
|
|
|
|
|
MYMENSINGH - SWAP J1 T4 AND T6, INSTALL MODIFIED MAI. 1 DST NOT SENDING DATA. |
|
|
|
|
|
RAI RADIO KEY ALWAYS ON. REMOVED KEY LINE FROM RADIO. |
|
|
|
|
|
PROBLEM DISAPPEARED |
|
|
|
|
|
VERIFIED RADIO TX RED TO TB3,1 - RX
GRN TO TB3,2 COM BLU TO TB3,4 |
|
|
|
|
|
.564 VAC FROM DHAKA ON RX LINE, RTU
UNDERSTANDS AND RESPONDS. HOORAY |
|
|
|
|
|
|
|
53 |
T |
10 |
15.00 |
TRIP TO TITAS AND TO BHALUKA
TO CO RADIO. SAME AS ON THE 9TH. DON'T KNOW WHAT WAS DONE WITH THE RADIO
BUT IT DIDN'T HELP. |
|
|
|
|
|
FINISH TYPING AND PRINTING
CONFIGURATION MANUAL. MAKE TRAINING OUTLINE, GATHER MATERIALS. |
|
|
|
|
|
|
|
54 |
W |
11 |
11.00 |
DELIVER TRAINING MANUAL TO SHAHINUL
ISLAM. TITAS- BHALUKA SHUTTLE. STILL
NO GO. |
|
|
|
|
|
PURCHASED "NOVA" COMPUTER
FROM "COMPUTERLAND" WITH NO KEYBOARD OR MONITOR. WILL USE THE KEYBOARD TO REPLACE THE
MISSING MATRIX ONE. WILL USE ORIG. MONITOR.
IT BOOTED CONCURRENT OK. RAN
SYSTEM. |
|
|
|
|
|
|
|
55 |
T |
12 |
11.00 |
TITAS - BHALUKA SHUTTLE - CAN SEE NO
IMPROVEMENT. IT IS NOT APPARANT WHAT CHANGES HAVE BEEN MADE WITH THE
RADIO. SYMPTOMS STILL THE SAME. |
|
|
|
|
|
BLOOD PRESSURE AT 150 /130 EVEN WITH
MEDS. ANGRY ALL OF THE TIME. |
|
|
|
|
|
INFORMED ROBERTS, SHAHADAD THAT I
WOULD NOT MAKE THE TRIP AGAIN UNTIL THEY WERE SURE RADIO WAS WORKING. |
|
|
|
|
|
NASIM PICKED UP COMPUTER, DELIVERED
TO GUEST HOUSE. |
|
|
|
|
|
LOAD SYSTEM AND SUPPORT SOFTWARE IN
THE NEW COMPUTER. |
|
|
|
|
|
BLOOD PRESSURE AT 150 /130 EVEN WITH
MEDS. ANGRY ALL OF THE TIME. |
|
56 |
F |
13 |
11.00 |
MET WITH SHAHADAD AND SHAHINUL FOR
CONFIG TRAINING. THEY WERE UNFAMILIAR WITH KEYBOARDING AND HAD NO KNOWLEDGE
OF DOS - EITHER MS OR CONCURRENT.
SHAHADAD COULD NOT TYPE. THEY
AGREED THAT THEY HAD INSUFFICIENT BACKGROUND TO PROCEED. |
|
|
|
|
|
WORKED ON REPAIRING MODULES. |
|
|
|
|
|
CONFIGURATION FILE CLEAN UP. |
|
|
|
|
|
|
|
57 |
S |
14 |
10.00 |
BHALUKA - WITH TITAS RADIO CLASS - MONOHORDI UHF SITE NOT WORKING SO NO SIGNAL
FROM DHAKA RETURNED TO GH TO WORK ON MODULES. TRACE DATA PATH THRU RDBs, MDB, HDB. |
|
|
|
|
|
|
|
58 |
S |
15 |
10.00 |
1/2 DAY
TRANSPORT STRIKE, WORK ON REPAIRS IN AM. |
|
|
|
|
|
PM - TAKE ROBERTS TO NORTHWEST
AIRLINES OFFICE TO RESERVE TICKETS HOME.
RADIOS NOT LIKELY TO WORK ANY TIME SOON. REWIRED DHAKA FOR 4 WIRE ELIMINATING RAI - AGAIN. |
|
|
|
|
|
|
|
59 |
M |
16 |
12.00 |
AM OPERATOR'S CLASS FOR TITAS GAS
ENGINEERS. ONLY 2 WERE FAMILIAR WITH KEY BOARD. ONE SEEMED
KNOWLEDGEABLE. WORKED WITH TWX AT
TITAS CENTRAL ATTEMPTING TO COMMUNICATE ON RADIO. SHAHADAD HOSSAIN AND SHAHINUL ISLAM DISCOVERED THAT THE TX AND
RX WERE REVERSED ON THE RADIO - ON ALL RADIOS. REWIRED FOR 3 WIRE
COMMUNICATION. |
|
|
|
|
|
BATTARY DEAD IN NEW COMPUTER, NASIM
TOOK TO COMPUTER LAND TO FIX. |
|
|
|
|
|
|
|
60 |
T |
17 |
15.00 |
AM OPERATOR'S CLASS FOR TITAS GAS ENGINEERS.
PM PROGRAMMED TEST EEPROM TO TALK JUST TO BHALUKA, TRISHAL AND MYMENSINGH. |
|
|
|
|
|
DROVE TO BHALUKA. RTU LISTEND AND RESPONDED TO THE THE MTU
WITH 3 WIRE SETUP. |
|
|
|
|
|
TRISHAL VHF - NO COMMUNICATION BECAUSE NO POWER. |
|
|
|
|
|
MYMENSINGH - RTU LISTENED TO MTU AND RESPONDED WITH 3 WIRE SETUP |
|
61 |
W |
18 |
15.00 |
AM OPERATOR'S CLASS. |
|
|
|
|
|
DHAKA TO CONFIRM MTU POLING RTU. INTERMITTANT COMM FAIL FROM SOMEWHERE. |
|
|
|
|
|
BHALUKA TO CONFIRM RTU STILL WORKING
- IT WAS. |
|
|
|
|
|
TRISHAL - NO POWER, IT WAS LATE AND TO DARK TO WORK. |
|
|
|
|
|
EVE DHAKA - DISCUSS 3 WIRE VS 4 WIRE
WITH JIM NEWSOME FROM DSC AND LARRY MEDLIN FROM AEROTRON IN ORDER FOR THE VHF
RADIOS TO WORK AT SPUR SITES, WE NEED 4 WIRE HOOKUP. CONTINUE TRYING TO TRACE DATA PATH THROUGH
THE CONFIGURATION FILES. |
|
|
|
|
|
DESIGN 4 WIRE MODS, ELIMINATING THE
RAI. |
|
|
|
|
|
|
|
62 |
T |
19 |
15.00 |
AM TITAS ENGINEERS FIELD TRIP TO
BHALUKA. |
|
|
|
|
|
PM CONVERT BHALUKA TO 4 WIRE AND TEST
COMM OOPS - NEED TO WIRE DHAKA TO 4 WIRE. |
|
|
|
|
|
EVE- TYPE OUT 4 WIRE CHANGE
DIRECTIONS. |
|
63 |
F |
20 |
16.00 |
AM DHAKA W/RADIO ENGINEER JIM
NEWSONE. CONVERT TO 4 WIRE. |
|
|
|
|
|
PM DRIVE 2.5 HRS TO ASHUGONJ, (DC -
DC CONVERTER REPORTED DEAD - CHECK IT OUT) |
|
|
|
|
|
ASHUGONJ - MAKE 4 WIRE MODS AND C/O CONVERTER - IT IS INDEED DEAD - REMOVE
CONVERTER AND RETUN IT TO THE GUEST HOUSE. CONFIR W/SHAHINUL ISLAM. DID NOT KNOW THE WORD
"VERIFY". REWRITE 4 WIRE
CONVERSION DIRECTION WITH SIMPLER VOCABULARY, MORE PICTURES. |
|
|
|
|
|
|
|
64 |
S |
21 |
16.50 |
AM TWX
OFFICE - VHF DRIVER ON NOVA COMPUTER HAVING PROBLEMS - ARRANGE FOR REPAIR |
|
|
|
|
|
TITAS
CENTRAL TO PU COMPUTER AND DELIVER TO BUSINESS LAND.
RETURN TO DHAKA, ADJUST LEVEL AND GAIN IN MTU IN CONJUNCTION WITH RADIO
TECHS. PU COMPUTER AT B/LAND. MEET WITH JAMAL HAMDANI AND DRIVE TO
BHALUKA. RADIO TECH - LARRY MEDLIN
FROM AEROTRON ADJUSTED VHF RADIOS.
JIM NEWSOME FROM DSC LIKEWISE. |
|
|
|
|
|
BHALUKA
- RTU HEARD MTU AND RESPONDED. DROVE TO TRISHAL. |
|
|
|
|
|
TRISHAL
- CONNECTED KEY WIRE PER J.H. - NO COMMON ATTACHED. COMMON THROUGH POWER SUPPLY. RTU HEARD
CENTRAL AND RESPONDED AFTER LOTS OF TINKERING WITH THE RADIOS. NOT SURE WHAT WAS DONE WITH RADIOS. IT DID NOT APPEAR THAT MTU UNDERSTOOD THE
RESPONSE FROM THE RTU (I.E. IT POLLED IT SEVERAL TIMES IN A ROW.) |
|
|
|
|
|
RETURNED TO
GUEST HOUSE, PACKED TO DEPART ON 22ND. |
|
|
|
|
|
|
|
65 |
S |
22 |
14.00 |
AM TWX OFFICE THEN MEETING
WITH J/H. AGREED TO STAY SINCE THERE WAS EVIDENCE THAT THE RADIOS
COULD BE MADE TO WORK. |
|
|
|
|
|
SET UP COMPUTER AT TITAS
CENTRAL. INSTALL THE SYSTEM MTU
EEPROM. FIX HOST TO ALLOW DIRECT
ACCESS TO MTU THROUGH MDBEDIT. IT
WORKED FOR ABOUT AN HOUR, THEN QUIT. |
|
|
|
|
|
EVE. - REVIEWED MTU PROGRAM AND DATA
PATH. REVIEWED MDBLIST1 AND 2. TYPED REPORT. |
|
|
|
|
|
|
|
66 |
M |
23 |
10.00 |
AM MEET W/JAMAL H. AT SONARGAON.
CLASS ON RADIO SYSTEM WITH TROUBLE SHOOTING BY JIM NEWSOME AND LARRY MEDLIN. |
|
|
|
|
|
PM - TITAS CENTRAL - MODIFY RTU FOR
CONSTANT CARRIER - LIFT PIN ON HEX INVERTER. MMDBEDIT WORKING JUST FINE
TODAY. NO GLITCHES IN HOST-MTU
COMMUNICATION. CONFIGURATION CHANGES
PER REQUEST. |
|
|
|
|
|
|
|
67 |
T |
24 |
16.00 |
AM REVIEW MTU PROGRAM - CORRECT TYPO
AT TARAKANDI. |
|
|
|
|
|
PM UPDATE CONFIGURATION OF TEXT FILES
TO MEET TITAS ENGINEER REQUEST. PRINT
FILES FOR CUSTOMER. MOVED SPARES TO GUEST HOUSE - SET UP REPAIR BENCH TO TEST RECALCITRANT SPARES. SPARE ASTs MISSING. WERE IN BOX AT TWX TO
BE INSTALLED AT SITES AS TWX WORKED ON RADIOS. THEY HAD NOT DONE THIS AND NO ONE KNOWS WHERE ASTs ARE. THEY CLAIM TO HAVE NEVER SEEN THEM NOR
KNOW WHAT THEY ARE. |
|
|
|
|
|
EVE - WRITE PROGRAM TO BENCH-TEST MTU
WITH A PAIR OF RTUs. RTU EEPROM PGRM
TO PUT DUMMY DATA OUT TO MTU, LIGHT LEDS.
IT WORKED. MTU TOOK IN DATA
AND STORED IT IN ALL CORRECTLY. |
|
|
|
|
|
PM UPDATE CONFIGURATION OF TEXT FILES
TO MEET TITAS ENGINEER REQUEST. PRINT
FILES FOR CUSTOMER. MOVED SPARES TO GUEST HOUSE - SET UP REPAIR BENCH TO TEST RECALCITRANT SPARES. SPARE ASTs MISSING. WERE IN BOX AT TWX TO
BE INSTALLED AT SITES AS TWX WORKED ON RADIOS. THEY HAD NOT DONE THIS AND NO ONE KNOWS WHERE ASTs ARE. THEY CLAIM TO HAVE NEVER SEEN THEM NOR
KNOW WHAT THEY ARE. |
|
68 |
W |
25 |
15.00 |
AM TITAS CENTRAL TO SET SKIP
FLAGS TO COM ONLY WITH BORROWED ASTS TO INSTALL AT REMOTE SITES. DRIVE TO TRISHAL. |
|
|
|
|
|
TRISHAL - 4 WIRE REWIRE TRISHAL AND DEMONSTRATED FOR NASIM. DRIVE TO MYMENSINGH |
|
|
|
|
|
MYMENSINGH - NASIM MADE 4 WIRE CHANGES
UNDER SUPERVISION. ALL
CONNECTIONS CONFIRMED. (RADIOS OUT OF
SERVICE. COULD NOT TEST
COMMUNICATION.) |
|
|
|
|
|
MICROWAVE LINK DOWN. BULB OUT AT 2,8. BAD CARD AT 2,11. SWAP
IN |
|
|
|
|
|
CARD FROM 36. |
|
|
|
|
|
EVENING - PROGRAM SPARE EEPROMS FOR
RTUs AND MTUs. |
|
|
|
|
|
|
|
69 |
T |
26 |
16.75 |
ALL DAY - JAMALPUR AND TARAKANDI. |
|
|
|
|
|
JAMALPUR - REPAIR SHIPPING DAMAGE - RACK HAD BROKEN LOOSE AND WAS LEANING IN THE
BACK OF THE CABINET. TOP "SHACKLE" HAD BROKEN. JURY-RIGGED REPAIRS. |
|
|
|
|
|
CATALOG OF DAMAGE - |
|
|
|
|
|
ELCO CONNECTORS BENT. |
|
|
|
|
|
BACK PANEL ABBRADED. |
|
|
|
|
|
CABINET DOOR SCRAPED WITH SOME GOUGES. |
|
|
|
|
|
WHITE PLASTER RESIDUE ON LIGHT COVERS |
|
|
|
|
|
SOME OF THE HANDELS WERE BENT. |
|
|
|
|
|
VERIFY POWER CABLE. CABLE TO INSTRUMENT CABINET INSTALLED
INSTEAD OF THE POWER CABLE. LOOSE
CABLE CARRYING 13.7 VDC LYING IN BOTTOM OF CABINET. TURNED OFF POWER AT THE
POWER SUPPLY. CORRECTED THE POWER HOOKUP. |
|
|
|
|
|
CHECKED LIGHTS. SEVERAL HAD BROKEN AND THE CLIPS WHICH
HELD THEM HAD BROKEN. USED UNUSED
POINTS TO REPLACE THE POINTS IN USE - MODIFIED CLIPS TO HOLD BULBS IN PROPER
POSITION. |
|
|
|
|
|
FIXED J1 T4 AND T6 WIRE SWAP, REMOVED
RAI AND DID 4 WIRE MODS. |
|
|
|
|
|
J7, T15 - J7, T4 = RX1 |
|
|
|
|
|
J7, T16 - J7, T3 = RX2 |
|
|
|
|
|
J7, T13 - J7, T6 = TX1 |
|
|
|
|
|
J7, T14 - J7, T5 = TX2 |
|
|
|
|
|
NO WIRE AVAILABLE TO CONNECT RADIO
KEY. RADIO NOT OPERATIVE ANYWAY - NO
INFORMATION AS TO WHY NOT BUT IT WOULD NOT OPERATE. |
|
|
|
|
|
LANDED LEADS FROM THE RADIO. |
|
|
|
|
|
TWX HAD NOT INSTALLED RTU, AST, NOR
MAI AT THIS SITE. |
|
|
|
|
|
TARAKANDI - |
|
|
|
|
|
RACK LOOSE IN CABINET, ELCO
CONNECTORS HAD SCORED THE BACK OF THE
CABINET. SOME GOUGES IN THE
DOOR. PUT RACK IN PLACE. CHECK FOR
DAMAGE WHICH MIGHT CAUSE OPERATIONAL PROBLEMS. THERE SEEMES TO BE NONE. |
|
|
|
|
|
VERIFY POWER SUPPLY AND DC-DC
CONVERTER. 27.5 VDC FROM PS - 23.7
VDC OUT OF CONVERTER (24VDC). TEST ALARMS- BAD CARD AT 11, SWAPPED WITH CARD
IN 36. REPLACED BROKEN BULBS WITH ONES FROM SPARE ALARMS. FIXED BROKEN CLIPS. ALL OK AFTER REPAIR. |
|
|
|
|
|
NOTE: WAXY BLUE/GREEN GOO ON J1-EVEN
SCREWS, LESS ON J1-ODD SCREWS, LESS ON J2-EVEN SCREWS AND JUST A LITTLE ON J2
ODD SCREWS. J3 ON ALL ARE BRIGHT AND
SHINEY. |
|
|
|
|
|
(NOTE: FLAT TIRE ON THE WAY HOME, IN
THE DARK, ON A BACK ROAD. REPAIRMAN
AT NEXT VILLAGE BURNED A HOLE IN THE TUBE.) |
|
|
|
|
|
JAMALPUR - REPAIR SHIPPING DAMAGE - RACK HAD BROKEN LOOSE AND WAS LEANING IN THE
BACK OF THE CABINET. TOP "SHACKLE" HAD BROKEN. JURY-RIGGED REPAIRS. |
|
70 |
F |
27 |
15.00 |
AM AT TWX SPOKE TO SHAHINUL - HE WILL DILIVER RTUs, ASTs, AND MODIFIED
MAIs TO JAMALPUR AND TARAKANDI. WHILE WAITING I SNOOPED AROUND THE TWX BACK
ROOM. FOUND A BOX WITH THE MISSING
ALARM AND LOGIC CARDS, TWO CALIBRATORS, THE COMPUTER-MTU CABLE, 100 SPARE
ALARM BULBS. (HOW ABOUT THAT? ALL OF THE STUFF TWX SAID THEY HADN'T RECEIVED
AND WHICH I SPENT A DAY AND A HALF SEARCHING FOR.) |
|
|
|
|
|
GAFFARGAON - |
|
|
|
|
|
CHECK POWER SUPPLY AND CONVERTER -
OK. |
|
|
|
|
|
INSTALL RTU, AST AND MAI. |
|
|
|
|
|
CHECK ALARM PANEL - |
|
|
|
|
|
TWO BULBS BROKEN. REPLACE WITH SPARE BULBS. REPAIR CLIPS |
|
|
|
|
|
NASIM - MAKE 4 WIRE MODS AT J7, FIX
J1 T4,T6. VERIFY CONNECTIONS -OK |
|
|
|
|
|
LAND RADIO CABLE IN TELEM
CABINET. RADIO TURNED OFF. NOT CLEAR
WHY. NO RESPONSE WHEN TURNED RADIO ON
AND TRIED TO CALL DHAKA. RAN WIRE FOR
RADIO KEY. |
|
|
|
|
|
(NOTE: BUS BLOCKING ROAD, STUCK IN MUD. GOT OUT TO PUSH, BUS
MOVED, DRIVER GOT BACK IN AND LEFT.
WALKED ABOUT 3 KM UNTIL COULD CATCH THE NEXT BUS.) |
|
|
|
|
|
|
|
71 |
S |
28 |
14.00 |
NETROKONA - |
|
|
|
|
|
CHECK POWER SUPPLY - AC SERVICE HAD
BEEN OFF FOR A NUMBER OF DAYS. BATTERIES HAD RUN LOW. NO GENERATOR TO CHARGE BATTERIES. POWER
SUPPLY ONLY PUTTING OUT 10VDC.
CONECTED POWER TO DC-DC CVTR. 10 VDC IN - 23.7 VDC OUT. |
|
|
|
|
|
4 WIRE MODS AND RADIO KEY WIRE. |
|
|
|
|
|
POWER BACK / TURNED ON. CONTINUE POWER SUPPLY CHECK. CHECKED POWER SUPPLY - 11.3VDC OUTPUT TO
CONVERTER CONVERTER OUTPUT = 23.7VDC. |
|
|
|
|
|
TWX HAD PREVIOUSLY WIRED INSTRUMENT
CABINET TO TELEMETRY CABINET - CONNECTIONS 1-12. NO POWER TO INSTRUMENT CABINET. 1-12 WERE STRAPPED NC. ANN CARDS SET UP FOR NO. AGREEMENT WAS FOR ALL INPUTS TO BE
NO. TWX WILL CHECK IT OUT. |
|
|
|
|
|
SOME ANN CARDS DID NOT SOUND HORN IN
A REASONABLE TIME, TWEEKED UNTIL DELAY ABOUT 10SEC. |
|
|
|
|
|
REPLACED BURNED OUT BULBS AND
REPAIRED BROKEN CLIPS. |
|
|
|
|
|
FLASHER CARD IN ALARM RACK 2 WOULD
NOT WORK AS EITHER MASTER OR SLAVE.
PUT ORIGINAL MASTER BACK. 1-24 FLASH.
23-36 NOT USED. NEED TO PUT IN
A SPARE FLASHER AT RACK 2. |
|
|
|
|
|
|
|
72 |
S |
29 |
15.00 |
AM - KILLED ANOTHER 2 HOURS WAITING
AT TWX. |
|
|
|
|
|
KISHORGONG - |
|
|
|
|
|
NO AC SERVICE AND NO GENERATOR.
BATTERIES LOW |
|
|
|
|
|
VERIFY THE 12VDC CABLE AND LAND WIRES
ON THE |
|
|
|
|
|
DC-DC CONVERTER. NOT ENOUGH POWER TO CONDUCT ALARM TEST. |
|
|
|
|
|
REWIRE FOR 4 WIRE, LAND WIRES FOR TX
AND RX FROM RADIO. |
|
|
|
|
|
NOT SURE WHAT IS GOING ON WITH THE
RADIO BUT CABLE NOT PULLED ALL OF THE
WAY TO THE RADIO. IT IS COILED IN THE OVERHEAD TRACK. |
|
|
|
|
|
INSTALL ONLY KEY LINE UNTIL CERTAIN
WHAT IS UP WITH THE RADIO. |
|
|
|
|
|
(8 HOURS ON THE ROAD, 2 HOURS AT TWX. 10 HOURS OF WASTED TIME!!) |
|
|
|
|
|
NO AC SERVICE AND NO GENERATOR.
BATTERIES LOW |
|
|
|
|
|
|
|
73 |
M |
30 |
15.00 |
AM - MEET AT TWX - GO TO STADIUM TO
PURCHASE SUPPLIES - DIODES. |
|
|
|
|
|
TRISHAL - TEST RADIO - NO POWER & NO GENERATOR. |
|
|
|
|
|
HAD BEEN ASSURED BY TWX THAT EVERYTHING
AT TRISHAL WAS WORKING BEFORE WE LEFT. TYPICAL. |
|
|
|
|
|
PM-EVE - REPAIR UNITS ON BENCH. SPARE
MTU, AND 2 RTUs RESURECTED. |
|
|
|
|
|
|
|
74 |
T |
31 |
16.00 |
SHERPUR - |
|
|
|
|
|
CHECK POWER SUPPLY - 12VDC OUTPUT. |
|
|
|
|
|
DC-DC CONVERTER - 23.4 VDC OUTPUT. |
|
|
|
|
|
MAKE 4 WIRE MODIFICATIONS, J1,T4 AND
J1,T6 CORRECT. |
|
|
|
|
|
LAND CABLE FROM RADIO. |
|
|
|
|
|
ALARM CHECK - |
|
|
|
|
|
MOVED RELAY FROM GROUP TO GROUP SINCE
ONLY 1 RELAY IN PANEL - NO SPARE RELAYS. |
|
|
|
|
|
REPLACED BROKEN BULBS AND FIXED
BROKEN CLIPS. |
|
|
|
|
|
REPLACED BAD ALARM CARD AT 10 |
|
|
|
|
|
REMOVED DC-DC CONVERTER TO TAKE TO
ASHUGHOJ. |
|
|
|
|
|
TRISHAL - INSTALLED RADIO KEY LINE |
|
|
|
|
|
MYMENSINGH - REPLACED MISSING ALARM CARD |
|
|
|
|
|
EVE - CONTINUE TO REPAIR MODULES |
|
|
|
|
|
|
|
75 |
W |
9/01/93 |
8.00 |
AM-PM - CONTINUE TO REPAIR MODULES |
|
|
|
|
|
SEVERE CHEST PAIN! |
|
|
|
|
|
HAD TICKET TO RETURN TO U.S. AGREED
TO STAY SINCE LARRY AND JIM ASSURED ME THAT THEY WOULD HAVE THE RADIOS
OPERATING IN A WEEK. ANYWAY, TOO MUCH
PAIN TO TRAVEL. |
|
|
|
|
|
|
|
76 |
T |
02 |
14.00 |
TWX ARRIVED AT ABOUT 10 - INVENTORY
MODULES WHILE WAITING. |
|
|
|
|
|
ASHUGONJ - |
|
|
|
|
|
INSTALL 12-24 CONVERTER BORROWED FROM
SHERPUR. |
|
|
|
|
|
CHECK OUT OK - 12VDC IN, 23.7 OUT.
ALARMS STILL WORK. |
|
|
|
|
|
LANDED WIRES TO TELEMETRY. |
|
|
|
|
|
SET RTU TX LEVEL TO .772 VAC PER
LARRY MEDLIN. |
|
|
|
|
|
NO INPUT OR OUTPUT SIGNAL AT
TELEMETRY CABINET. |
|
|
|
|
|
CHECKED IN RADIO ROOM. TELEMETRY CABLE LIFTED. NOT CONNECTED TO RADIO. CHANNEL BEING USED TO TEST ANOTHER UHF
STATION. CANNOT TEST SCADA LINK. |
|
|
|
|
|
MONOHORDE - |
|
|
|
|
|
PICK UP UHF RECEIVER FOR JIM
NEWSOME. MET WITH JIM AND LARRY AT
SONARGAON. |
|
|
|
|
|
|
|
77 |
F |
03 |
12.00 |
AM-PM - REPAIR MODULES, SORT OUT
COMPATABLE MTUCOMM AND MDBLIST COMPATABILITY. |
|
|
|
|
|
|
|
78 |
S |
04 |
14.00 |
MYMENSINGH - |
|
|
|
|
|
LEVEL INPUT AT 0db. OUTPUT AT .333VAC
- WOULD NOT CHANGE WHEN TWEEKED LEVEL POT.
CALLED JIM AT BHALUKA. TX AND
RX SWITCHED AT PUNCH BLOCK. I CHANGED
THEM IN TELEMETRY CABINET SINCE IT WAS MUCH EASIER THAN AT RADIO. NOTE: COLOR
SCHEME FOR RADIO CABLE AGREED UPON WITH SHAHADAD HOSSAIN WAS: |
|
|
|
|
|
TX1=RED |
|
|
|
|
|
TX2=GREEN |
|
|
|
|
|
RX1=YELLOW |
|
|
|
|
|
RX2=BLUE OR BLACK. |
|
|
|
|
|
THIS SCHEME HAS NOT - NOT!! -
BEEN FOLLOWED AT ANY SITE. THE WIRES
HAVE BEEN LANDED ON THE PUNCH BLOCK IN ANY ORDER, WITHOUT REGARD TO
COLOR. IT IS IMPOSSIBEL TO TELL WHICH IS TX AND WHICH IS RX WITHOUT CHECKING THE
INPUT ON THE PUNCH BLOCK. IN SOME
CASES, THE PUNCH BLOCK HAS BEEN INCORRECTLY WIRED TO THE RADIO SO THERE IS NO
WAY TO TELL WHICH IS TX, WHICH IS RX, WHICH IS E, NOR WHICH IS M. CD AND SDI OK.CONTINUED ON PAGE 20 |
|
|
|
|
|
AGREED WITH JIM NEWSOME TO SET RTU
OUTPUT AT .25VAC. ANY OTHER ADJUSTMENT DONE THROUGH UHF AT BHALUKA. (RADIO PEOPLE TO TAKE CARE OF LEVELS AFTER
RTU LEVEL SET. RADIOS HAVE SEVERAL
CONTROLS WHERE THIS CAN BE ACCOMPLISHED.) |
|
|
|
|
|
|
|
79 |
S |
05 |
16 |
DHAKA - SET MTU TO TALK TO MYMENSINGH AND TARAKANDI. DRIVE TO MYMENSINGH. |
|
|
|
|
|
MYMENSINGH - RTU RESPONDED TO MTU AND MTU WENT ON POLING OTHER SITES IN THE
LOOP. APPEARED TO BE WORKING. WITH JIM AND LARRY, SET LEVEL AT .25 VAC
AGAIN - WITH 600 OHM RESISTANCE AT BRIDGE. DRIVE TO TARAKANDI - |
|
|
|
|
|
TARAKANDI - WIRES FROM RADIO TO PUNCH
BLOCK IN WRONG |
|
|
|
|
|
POSITION. FIXED WITH DIRECTION FROM
JIM NEWSOME BY PHONE. |
|
|
|
|
|
RTU WAS INSTALLED BY SHAHINUL
ISLAM. SHUNTED TO BE STATION 15. CHANGED TO STATION 17 PER STATION
PLAN. |
|
|
|
|
|
RTU IN RACK NOT SCANNING ALL
SCANNERS. REPLACED WITH A SPARE - OK. |
|
|
|
|
|
TURNED ON CONSTANT CARRIER, SET
OUTPUT TO .25 VAC WITH 600 OHM ATTENUATION AT BRIDGE PER AGREEMENT W/JIM
NEWSOME. |
|
|
|
|
|
MAI CHANNEL 1-4 OVERRANGING. DISCOVERED COLD SOLDER JOINT. REPAIRED. OK |
|
|
|
|
|
RTU HEARD THE MTU BUT DID NOT RESPOND. NO BAD MSG LED. |
|
|
|
|
|
TALKED TO DHAKA ON RADIO PHN. POWER HAD GONE OUT. MTU RESET. |
|
|
|
|
|
|
|
80 |
M |
06 |
15.50 |
DHAKA - NO REMOTE RESPONDING. SET
SKIP FLAGS TO JUST POLL JAMALPUR AND TARAKANDI |
|
|
|
|
|
DRIVE TO JAMALPUR - 4.5 HOURS - MID
AFTERNOON. |
|
|
|
|
|
JAMALPUR - |
|
|
|
|
|
RX AND TX NOT LANDED CORRECTLY. FIXED PER AGREEMENT WITH TWX (I.E. RED=TX1, GREEN=TX2, YELLOW=RX1,
BLUE =RX2) |
|
|
|
|
|
TURNED ON RTU CARRIER AND SET OUTPUT
LEVEL TO .25VAC WITH 600 OHM LOAD PER AGREEMENT WITH JIM NEWSOME. |
|
|
|
|
|
CHECKED OUT SCANNERS - RTU HITTING
THEM ALL. |
|
|
|
|
|
RAN GREEN AND WHITE PAIR FOR RADIO
KEY TO TB3. |
|
|
|
|
|
ATTACHED TEMPORARY KEY WIRE TO GREEN
AND WHITE PAIR AND RAN WIRE TO E-LEAD ON VHF RADIO PER LARRY MEDLIN. |
|
|
|
|
|
ADJUSTED LEVELS PER LARRY'S
INSTRUCTIONS OVER THE RADIO PHONE.
RAISED RTU OUTPUT TO 0DB PER LARRY. |
|
|
|
|
|
RTU LISTENED AND RESPONDED DURING
TEST WITH BOTH MANUAL KEYING AT THE RADIO AND WITH KEYING FROM THE RTU. E LEAD TO COMMON WHEN RADIO KEYS - OK. |
|
|
|
|
|
SET MODEM CARRIER ONLY WHEN TX. |
|
|
|
|
|
|
|
81 |
T |
07 |
14.50 |
AM-TITAS, SET SKIP FLAGS FOR MTU TO ONLY POLE SHERPUR.
STOP AT TWX - 1 HR. DRIVE TO
SHERPUR 4.5 HOURS. |
|
|
|
|
|
SHERPUR - RUN RADIO KEY WIRE AND RADIO COMMON WIRE. |
|
|
|
|
|
VERIFY TX AND RX WIRES CORRECT. RADIO CREW ADJUSTING THE RADIO. IT WAS NOT WORKING. WENT IN TELEMETRY ROOM TO MAKE NOTES. RADIO CREW AT TARAKANDI LEFT WITHOUT
TELLING ME AND WITHOUT CHECKING OUT SCADA RADIO LINK. |
|
|
|
|
|
(9 HOUR ON THE ROAD PLUS WAITING
AROUND FOR 2 HOURS TO ACCOMPLISH NOTHING!!!
TOTAL 14.5 HOURS.) |
|
|
|
|
|
|
|
82 |
W |
08 |
10.00 |
REPAIRS TO RTUS AND MTU. SPARE MTU STOPPED WORKING. RESURECTED. RTUS STOPPED WORKING.
RESURECTED 2. |
|
|
|
|
|
|
|
83 |
T |
09 |
10.50 |
RAPAIRED AST. ANOTHER RTU. COULD NOT
FIND THE FAULT IN THE DST. |
|
|
|
|
|
|
|
84 |
F |
10 |
10.00 |
AM - TITAS OFFICE TO CHECK MTU
COMMUNICATION. RADIOS DOWN. NOTHING WAS WORKING. |
|
|
|
|
|
PM - MEET BILL AT AIRPORT. GO TO TWX OFFICE AND HOTEL |
|
|
|
|
|
|
|
85 |
S |
11 |
10.75 |
AM - MEET AT TITAS OFFICE, GO OVER
SETUP |
|
|
|
|
|
PM - WORK ON REWORK OF CONFIGURATION
FILES AND EXPLAIN CHANGES REQUESTED BY TITAS. |
|
|
|
|
|
|
|
86 |
S |
12 |
10.00 |
CONTINUED REPAIRS TO MODULES WHICH
HAD DIED DURING PREVIOUS 3 MONTHS.
MAKE PLAN CHANGES AT TARAKANDI.
WRITE REPORTS. |
|
|
|
|
|
|
|
87 |
M |
13 |
12:00+ |
NO DAILY NOTES FOR 13TH TO 18TH. WROTE OUT LOG FROM MEMORY ON 18TH. ALL DAYS AT LEAST 10 HRS. |
|
|
|
|
|
|
|
88 |
T |
14 |
12:00+ |
MET AT TITAS ENGINEERING OFFICE WITH
MR. CHAKMA AND OTHERS RE ADDED SIGNALS AT TARAKANDI. TOMORROW TO TARAKANDI |
|
|
|
|
|
PM - CONTINUE REQUESTED MODIFICATIONS
AND MODULE REPAIRS |
|
|
|
|
|
|
|
89 |
W |
15 |
14:00+ |
TARAKANDI- (4 HR DRIVE!) |
|
|
|
|
|
TOOK YOUNG
TITAS ENGINEER IN CHARGE OF THE SIGNAL INPUTS. SHAHINUL ISLAM, SHAHADAD HOSSAIN AND THE TWX TECHNICIAN, MR.
JUHUNGI |
|
|
|
|
|
JUHUNGI
CONNECTED INPUTS TO TELEMETRY PANEL.
ADJUSTED STRAPPING ON ALARM CARDS TO ACCOMODATE VARIOUS NO AND NC
SIGNALS. (I SHOWED MR JUHUNGI HOW TO "PIGTALE"
POWER TO INPUT PANEL AND SUPPLIED WIRE NUTS FOR THAT PURPOSE. NO PREVIOUS AC EXPERIENCE!) |
|
|
|
|
|
TOOK YOUNG
TITAS ENGINEER IN CHARGE OF THE SIGNAL INPUTS. SHAHINUL ISLAM, SHAHADAD HOSSAIN AND THE TWX TECHNICIAN, MR.
JUHUNGI |
|
90 |
T |
16 |
14.00+ |
TARAKANDI- (YET AGAIN!) |
|
|
|
|
|
JUHUNGI
CONTINUED REPAIRS. WITHOUT CONSULTING
ME, SHAHINUL ISLAM TURNED ON POWER TO INPUT
PANEL. SEVERAL FIELD DIVICES WERE NOT
CONNECTED AND SO WENT INTO ALARM.
THERE WAS CONFUSION RE WHICH SIGNALS WERE ACTUALLY IN USE AND WHICH WERE
NOT. TITAS EMPLOYEES HAD SOME
DISCUSSION ON THE MATTER. |
|
|
|
|
|
|
|
91 |
F |
17 |
12.00+ |
TARAKANDI- (YET AGAIN!) |
|
|
|
|
|
RETURNED AGAIN WITH JUST MR. JUHUNGI
TO WORK ON THE RADIO. WITHOUT THE INTERFERANCE OF THE TITAS ENGINEERS WE
FIXED TX AND RX FROM BRIDGE. ALSO,
PIN ON BRIDGE BROKEN. FIXED AND
RETWISTED WIRE OVER PIN (TWX HAD NO WIRE WRAP TOOL. ALL WORK DONE WITH
PLYERS. WITH J/H GIVING DIRECTIONS ON
RADIO PHONE.) VERIFIED RADIOS
WORKING. NO CONSENSUS @ TWX REGARDING
WHICH SIGNALS TO CONNECT. |
|
|
|
|
|
(ARRIVED IN DHAKA ABOUT 9:30 AND WENT
STRAIGHT TO SHAHIN'S WEDDING. MISSED
THE CEREMONY BUT MADE THE RECEPTION - WHICH WENT ON FOR AT LEAST 3 MORE
DAYS.) |
|
|
|
|
|
|
|
92 |
S |
18 |
10.00+ |
TWX OFFICE - WHILE WAITING FOR OTHERS
TO ARRIVE, LOOKED IN "BACK ROOM" FOR BOXES TO USE FOR PACKING &
LOCATED THE MISSING ASTs. |
|
|
|
|
|
INVENTORIED THE PREVIOUSLY
UNDISCOVERED PARTS - RONAN, MOSLEY, AND TELEPRODUCTS. (TWX WAS UPSET THAT I
HAD SNOOPED. BUT, THEY COULDN'T
COMPLAIN TOO MUCH. ALSO FOUND SOME
SECURITY WANDS THEY HAD ORDERED FOR THE GOVERNMENT AND WHICH HAD GONE
MISSING. SUSPECT THAT THESE ITEMS
WERE INTENDED FOR EVENTUAL RESALE "OFF THE BOOKS".) |
|
|
|
|
|
|
|
93 |
S |
19 |
10.00 |
TRISHAL - |
|
|
|
|
|
RAN COMMON WIRE AND KEY WIRE TO
RADIO. TEST RADIO. |
|
|
|
|
|
AT DIRECTION OF MR. HAMDANI, KEYED
RADIO MANUALLY AND TURNED ON CONSTANT CARRIER FROM RTU. ADJUSTED LEVELS PER MR HAMDANI'S
DIRECTION. AFTER SOME TIME
COMMUNICATION WITH DHAKA WAS ESTABLISHED. |
|
|
|
|
|
MOVED TO SONARGAON HOTEL IN PM. BEGAN INVENTORY. |
|
|
|
|
|
|
|
94 |
M |
20 |
14.00 |
JAMALPUR - |
|
|
|
|
|
JURY-RIGGED CABLE FROM RADIO COMMON
TO RADIO GROUND AND RE-RIGGED RADIO KEY LINE. |
|
|
|
|
|
SOLDERED DELAY DIODES INTO RTU AT
S97, 96, AND 95. |
|
|
|
|
|
TURNED ON RTU CONSTANT CARRIER. |
|
|
|
|
|
COULD NOT COMMUNICATE WITH DHAKA
UNTIL ABOUT 2:30 P.M. |
|
|
|
|
|
NO CARRIER FROM TARAKANDI. NO POWER AT TARAKANDI. J/H DIRECTED THEM
TO ENGAGE GENERATOR. |
|
|
|
|
|
TARAKANDI TURNED ON. CARRIER CAME IN VERY DIRTY ON SCOPE WITH
AN OVERLAYING BEEP FROM THE BATTERY ALARM - NO AC, OPERATING ON BATTERY POWER
ONLY. RTU RESPONDING ABOUT EVERY 4TH
TIME |
|
|
|
|
|
CARRIER BEGAN TO "COME AND
GO", JUST BEFORE IT GOES OFF
THERE IS A SPIKE ON SCOPE. |
|
|
|
|
|
JUMPERED KEY ON AT RADIO PER J.H. -
NO CHANGE. |
|
|
|
|
|
AT MR. HAMDANI'S DIRECTION, REMOVED
YELLOW WIRE FROM PS TERMINAL BLOCK ON THE VHF RADIO, F3. PS BEEP GONE. SINE WAVE FROM MTU REGULAR, RTU RESPONDS EVERY TIME. |
|
|
|
|
|
REMOVED RADIO KEY JUMPER, WATCHED RTU
CONTINUE TO RESPOND EVERY TIME. WHILE
OBSERVING THE SINE WAVE FROM THE MTU, IT WENT FLAT. |
|
|
|
|
|
AT MR. HAMDANI'S DIRECTION, ATTEMPTED
TO COMMUNICATE WITH TARAKANDI BY VOICE OVER RADIO F3. NO ONE RESPONDED, ALTHOUGH I COULD HEAR
THE REPEATER KEY OCCASIONALLY. |
|
|
|
|
|
WAITED FOR DHAKA TO MAKE
ADJUSTMENTS. AFTER SOME TIME, SINE
WAVE REAPPEARED, ALTHOUGH MORE RAGGED THAN BEFORE. |
|
|
|
|
|
SINE WAVE DISAPPEARED, SIGNAL
FLAT. REAPPEARED, WENT FLAT -
REPEATED SEVERAL TIMES - WENT FLAT AND DID NOT RETURN. TRIED TO GIVE MR. HAMDANI A BLOW BY BLOW
DESCRIPTION BUT ALL HE SAID WAS "CALM DOWN". HE INFORMED ME THAT THE RADIO WAS
WORKING. NOT CLEAR WHERE HE RECEIVED
HIS INFORMATION. |
|
|
|
|
|
VERIFIED THAT BATTERY
"BEEP" WIRE NOT TOUCHING ANYTHING.
IT WAS NOT. |
|
|
|
|
|
LARRY MEDLIN CALLED ON F2. AFTER SOME ADJUSTMENT, STEADY SINE WAVE
AND MTU CAME THROUGH CLEARLY. FSK
FROM MTU CLEAR, AND RESPONSE FROM RTU CLEAR. |
|
|
|
|
|
LARRY LEFT TARAKANDI TO RETURN TO
DHAKA. ABOUT 15 MINUTES LATER, THE
RADIO FAILED AGAIN AND THE DIRTY SINE WAVE APPEARED AGAIN, THEN WENT FLAT. |
|
|
|
|
|
NO ONE AT DHAKA OR AT TARAKANDI
RESPONDED. |
|
|
|
|
|
MR. JUHUNGI WIRED ANNUNCIATOR PANEL
TO THE INPUT PANEL. TESTED STRAPPING
AND ADJUSTED AS NEEDED. |
|
|
|
|
|
#6 DOES NOT CHANGE STATE - ALWAYS IN
ALARM. WHEN LIFT WIRE FROM INPUT
PANEL, IT WORKS FINE. |
|
|
|
|
|
#8 LIKEWISE. |
|
|
|
|
|
TWX WILL NEED TO CHECK WIRING ON
INPUT PANEL. |
|
|
|
|
|
|
|
95 |
T |
21 |
12.00 |
AM - BHALUKA - FINAL DEMO - NO POWER. BATTERIES DEAD. GENERATOR STOLEN. J/H
VERY TESTY. TITAS REPS, GOVERNMENT
REPS, AND TWX ENGINEERS SUCRRYING ABOUT TRYING TO GET POWER. I WENT IN GUARDROOM TO STAY OUT OF THE
WAY. AFTER ABOUT 2 HOURS TITAS
ENGINEER FOUND OUT THAT THE NATIONAL ELECTRIC COMPANY HAD TURNED OFF TITAS
POWER FOR NON PAYMENT. |
|
|
|
|
|
BACK TO TITAS WITH J/H THEN TO
SONARGAON |
|
|
|
|
|
CONFIGURE REPAIRS, WORK WITH WKD ON
EQUIP INVENTROY. ARRANGE TO RETURN
ON 23RD. |
|
|
|
|
|
|
|
96 |
W |
22 |
10.00 |
INVENTORY CHECK. |
|
|
|
|
|
PICK UP ITEMS STORED AT GUEST HOUSE
AND REVIEW DATA PATH. |
|
|
|
|
|
PROOF READ CONFIGURATION CHANGES
REQUESTED BY CUSTOMER. |
|
|
|
|
|
WRITE DIRECTIONS FOR TWX REGARDING
INVENTORY AND WHAT IS NECESSARY TO CORRECT CONNECTIONS - I.E. REPLACING 4
WIRE CABLES AT VHF SITES WITH 6 WIRE CABLES AND CONNECTIONS. |
|
|
|
|
|
NOTES ON INPUTPANEL PROBLEMS. |
|
|
|
|
|
PACK. |
|
|
|
|
|
|
|
97 |
T |
23 |
8:00 |
PREPARED MATERIALS TO TURN OVER TO
TWX. TWX SCHEDULED TO COME AT 8:30 TO
TRANSPORT EQUIPMENT TO TITAS GAS OFFICE.
SHOWED UP AT 11:00. TURNED
EQUIPMENT OVER TO MR. NASIM AND MR. JUHUNGI.
DROVE TO AIRPORT WITH WKD NASIM & JUHUNGI - AND DEPARTED |
|
|
|
|
|
|
|
98 |
F |
24 |
16:00 |
RETURN TO LA, CROSSING DATE
LINE. TURNED IN EQUIP AT RONAN AND
REPORTED. |
HOME
|